How to Use the Master Services Contract
Main_Content
Master Services Contract: Work Order Process
Overview:
The Independent Verification & Validation (IV&V) work order process is intended to describe the process by which DoIT will utilize the IV&V Master Services Contract to enable and administer IV&V. As noted below, this process will be carried out by the DoIT (including support from the IV&V Project Manager, Procurement and Legal Advisors, and the Acting Director/Assistant Director for the Enterprise Program Management Office). The process will also rely on the support from the Agency which is to be subject of the IV&V.
If this is your first time using this contract, or a master contract of this type, feel free to email:
stephen.liberati@maryland.gov and request assistance from the Contract Manager, who will be happy to call you and help you work through these steps.
Step #
|
Description
|
Responsibile Party
|
---|
1
| Requirements documentation is completed via the Master IV&V Services Contract Template which serves as the justification for the IV&V need.
| Contract Manager with Support from the Agency As Needed
|
---|
2
| The determination of need is reviewed and accepted and an intake request is created.
| Contract Manager with Support from the Agency As Needed
|
---|
3
| Resource requirements determination.
| Contract Manager with Support from the Agency As Needed
|
---|
4
| Prepare and submit draft of Work Order (WO) (with requirements) to DoIT EPMO IV&V.
| Contract Manager in tandem with DoIT Procurement
|
---|
5
| DoIT EPMO IV&V finalizes WO and DoIT Procurement issues to master contractors.
| DoIT Procurement
|
---|
6
| Submission of proposal/resumes/pricing (package) in response to WO to DoIT Procurement Officer.
| TO Master Contractors
|
---|
7
| Administrative review of packages and uploads into Google folder.
| DoIT Procurement
|
---|
8
| Technical review of proposal/resumes.
| Contract Manager and any identified selection committee
|
---|
9
| Pricing is considered for those submissions found technically qualified.
| Contract Manager and any identified selection committee
|
---|
10
| MOU and/or SOW is developed and executed.
| Contract Manager with signature from the Agency
|
---|
11
| TO Contractor(s) are notified of selection confirmation
| DoIT Procurement
|
---|
12
| WO documentation is drafted and sent to TO Contractor for signature:
- Issued Work Order Agreement
-
Non-Disclosure Agreement (must be signed by TO Contractor and resource(s))
-
Computer Use Agreement (if agency specific equipment is required)
-
Criminal Background Check Affidavit
| DoIT Procurement
|
---|
13
| TO Contractor returns documentation to Procurement Officer who confirms signatures
| DoIT Procurement Officer
|
---|
14
| Submission of Work Order Agreement and NDA to WO Manager for signature.
| DoIT Procurement Officer
|
---|
15
| Execution of documents with submission back to Procurement Officer.
| Contract Manager
|
---|
16
| Provision of Work Order documentation to Finance for creation of FMIS BPO.
| DoIT Procurement Officer
|
---|
17
| Executed documents sent to TO Contractor with notice to proceed.
| DoIT Procurement Officer
|
---|
18
| TO contractor reports to respective Agency Point of Contact (POC) as of NTP start date.
| Contract Manager
|
---|
Post-Award |
---|
1
| Work Orders are issued to document the need, period of performance, staffing and deliverables.
| Contract Manager with Support from the Agency As Needed
|
---|
2
| TO contractor submits deliverables in support of IV&V for review and acceptance.
| Contract Manager with Support from the Agency As Needed
|
---|
3
| TO contractor submits invoices for review and acceptance to DoIT Finance for Work Order Manager approval.
| Work Order Manager
|
---|
4
| DoIT Finance invoices respective agency for payment of services on the agreed upon terms of the MOU or SOW.
| DoIT Finance, Agency Support, IV&V PM
|
---|