What is a Major IT Development Project?

An MITDP is an information technology development project that meets one or more of the following criteria:

  1. The estimated total cost of development equals or exceeds $5,000,000;
  2. The project is undertaken to support a critical business function associated with the public health, education, safety, or financial well–being of the residents of Maryland; or
  3. The Secretary determines that the project requires the special attention and consideration given to a major information technology development project due to:
    1. The significance of the project’s potential benefits or risks;
    2. The impact of the project on the public or local governments;
    3. The public visibility of the project; or
    4. Other reasons as determined by the Secretary.

MITDPs Do Not Include:

  1. Technology that is reoccurring, standard operating technology
  2. Expedited Projects, another category of major IT projects funded by the state

Projects determined to qualify as MITDPs are eligible for funding from IT Investment Fund, required to comply with the State’s System Development Life Cycle (SDLC), and subject to oversight by DoIT’s MITDP Oversight Division. To learn more, review the MITDP policies.

List of Current MITDPs

The MITDP portfolio list compiles all of the state’s major information technology development projects (MITDPs) that are in progress.

Deadlin​es

Disclaimer: All dates subject to change.

Monthly Deadlines​​

Deadline Item
Monthly by the 10th Monthly project Health Assessment Report (HAR)
Monthly by the 10th Monthly project Financial Reporting

Annual Deadlines​​

Deadline Item
June 13, 2025 Pre-FY27 Funding Request Rebaseline (If Necessary)
June 30, 2025 Baseline Forecast for FY26 (Formerly Initial Monthly Forecast, IMF)
July 25, 2025 Project Request for new FY26 or FY27 MITDPs
July 25, 2025 Funding Request for FY27 (Formerly Information Technology Project Request, ITPR)
July 31, 2025 All FY25 Charges in FMIS
~ Nov 10 Mid Year Report Project Narrative